Project Location

East Ferry St, New Haven, CT, USA

Solicitation Status: Current
Project Phase: Bidding
Pre Bid Meeting Date: 02/21/2018 10:00 AM
Bid Date: 03/07/2018 10:00 AM
Notice to Proceed: 03/30/2018
End Date: End Date

The proposed project includes the cured-in-place pipe (CIPP) lining rehabilitation of approximately 3,030 feet of 24" sewer mains.
Budget: $0

Description

The proposed project includes the cured-in-place pipe (CIPP) lining rehabilitation of approximately 3,030 feet of 24" sewer mains.
Project Group:
Construction
 
Town Of Project:
New Haven
 
Special Instructions:
**PLEASE NOTE**

All plans & specs posted in the Project Document Section are strictly for REFERENCE ONLY.

All bidders are required to purchase the Plans & Specs as per the attached Bid Invitation.
 
Project Manager:
Ricardo Ceballos
 
Project Manager Address:
GNHWPCA
260 East Street
New Haven, CT 06511
 
Project Manager Email:
rceballos@gnhwpca.com
 
Contract Duration
90
   

Project Documents

SSR 2018-02 Bid Invitation website.pdf SSR 2018-02 FINAL BID DOCUMENT website.pdf SSR 2018-02 Quinnipiac CIPP Lining Plan Pick Up Sheet.pdf