2025 Collection System CIPP Lining Rehabilitation – HML04 (Project No: SSR 2025-02)
Solicitation Status:
Current
Current
Project Phase:
Bidding
Bidding
Pre Bid Meeting Date:
09/19/2025 10:00 am
09/19/2025 10:00 am
Bid Date:
10/03/2025 10:00 am
10/03/2025 10:00 am
Notice to Proceed:
11/03/2025
11/03/2025
End Date:
06/30/2026
06/30/2026
Budget:
Description
The purpose of the proposed project is to rehabilitate approximately 9,700 feet of small-diameter sanitary sewer pipes that have been determined to be structurally compromised, based on cleaning and CCTV inspections conducted by GNHWPCA staff. The pipes, ranging from 8” to 15” in diameter, are primarily vitrified clay pipe (VCP) and are located within sub-shed HML04 in Hamden, adjacent to Lake Whitney—a priority area due to its proximity to sensitive environmental and residential zones.
- Project Group:
Construction - Town Of Project:
New Haven - Special Instructions:
***PLEASE NOTE*** All Plans & Specs posted in the Project Document Section are strictly for REFERENCE ONLY. All bidders are required to purchase the Plans & Specs as per the attached Bid Invitation.
- Project Manager:
Ricardo Ceballos - Project Manager Address:
GNHWPCA 260 East Street New Haven, CT 06511 - Project Manager Email:
rceballos@gnhwpca.com
- Contract Duration:
240 Days