East Shore Water Pollution Abatement Facility Bar Screen Replacement (Project No: SSF – 2015-01 )
Solicitation Status:
Awarded
Awarded
Project Phase:
Completed
Completed
Pre Bid Meeting Date:
06/18/2015 2:00 pm
06/18/2015 2:00 pm
Bid Date:
07/09/2015 10:00 am
07/09/2015 10:00 am
Notice to Proceed:
08/01/2015
08/01/2015
End Date:
03/01/2016
03/01/2016
This project involves the demolition of existing Bar Screens and supply and installation of two (2) new Bar Screens at the East Shore Water Pollution Abatement Facility. The scope also includes replacement of slide gates and repairs to the floor grating system.
Budget: $500,000
Description
This project involves the demolition of existing Bar Screens and supply and installation of two (2) new Bar Screens at the East Shore Water Pollution Abatement Facility. The scope also includes replacement of slide gates and repairs to the floor grating system.
- Project Group:
Construction - Town Of Project:
New Haven - Special Instructions:
*PLEASE NOTE* All Plans & Specs posted in the Project Document Section are strictly for Reference Only. All Bidders are required to purchase these plans & specs as per the attached Bid Invitation.
- Project Manager:
Joe Megale - Project Manager Address:
260 East Street, New Haven, CT - Project Manager Email:
engineering@gnhwpca.com
- Contract Duration:
213