Construction Projects

The Greater New Haven Water Pollution Control Authority (GNHWPCA) funds and maintains a Capital Improvement Program (CIP) to ensure that its sewer systems are reliable, safe and efficient while at the same time contributes to protect the environment. Funding for the CIP is provided through the following sources: GNHWPCA’s annual operating budget, revenue bonds, grant reimbursements and grant/loan programs provided by the Connecticut Department of Environmental Projection (DEP) along with other incidental projects required by state agencies such as the Connecticut Department of Transportation (DOT.) In this section, you will find detailed information on major construction projects currently underway in the GNHWPCA Service Area. The information will provide project purpose and description as well as GNHWPCA contacts. (project descriptions from intranet projects page “community description” )
Mitchell Dr, New Haven, CT 06511, USA

Humphrey Street & Mitchell Drive Pump Stations Rehabilitation Project (Project No: SSF – 2017-03 )

Solicitation Status:
Awarded
Project Phase:
Completed
Pre Bid Meeting Date:
03/22/2018 10:00 am
Bid Date:
04/12/2018 10:00 am
Notice to Proceed:
05/28/2018
End Date:
02/22/2019
Renovation upgrades will include replacing wet well/dry well arrangements with a duplex submersible pump station design, replacement of pole mounted controller cabinet with a standalone control cabinet, back-up generator and fenced enclosure.
Budget: 0

Description


Renovation upgrades will include replacing wet well/dry well arrangements with a duplex submersible pump station design, replacement of pole mounted controller cabinet with a standalone control cabinet, back-up generator and fenced enclosure.

  • Project Group:
    Construction
  • Town Of Project:
    New Haven
  • Special Instructions:
    **PLEASE NOTE** All Plans and Specs posted in the Project Document Section are strictly for REFERENCE ONLY. All bidders are required to purchase the Plans and Specs as per the attached Bid Invitation.
  • Project Manager:
    Tom Sgroi
  • Project Manager Address:
    GNHWPCAtsgroi@gnhwpca.com,e 260 East Street New Haven, CT 06511
  • Project Manager Email:
    engineering@gnhwpca.com
  • Contract Duration:
    270