I/I Rehab Hamden & East Haven (Project No: CWF 2016-06)
Solicitation Status:
Current
Current
Project Phase:
Completed
Completed
Pre Bid Meeting Date:
08/19/2020 10:00 am
08/19/2020 10:00 am
Bid Date:
09/15/2020 11:00 am
09/15/2020 11:00 am
Notice to Proceed:
01/05/2021
01/05/2021
End Date:
07/04/2022
07/04/2022
Budget:
Description
This project consists of sanitary sewer rehabilitation in the Middle Thorpe Drive Sewershed and Upper Thorpe Drive Sewershed (Paradise Avenue Easement) in Hamden and Meter Area 5, 9 and 13 Sewersheds in East Haven. Rehabilitation will include cured-in-place lining of approximately 25,000 linear feet of sanitary sewer, temporary bypass pumping, rehabilitation of approximately 142 service lateral/sewer main connections; rehabilitation or alterations to approximately 251 manholes, construction of access road and related work activities.
- Project Group:
Construction - Town Of Project:
Hamden & East Haven - Special Instructions:
***PLEASE NOTE*** All Plans & Specs posted in the Project Document Section are strictly for REFERENCE ONLY. All bidders are required to purchase the Plans & Specs as per the attached Bid Invitation.
- Project Manager:
Mario Ricozzi - Project Manager Address:
GNHWPCA 260 East Street New Haven, CT 06511 - Project Manager Email:
mricozzi@gnhwpca.com
- Contract Duration:
545 Days
Project Documents:
- CWF-2016-06-FINAL-102-18-Invitation.pdf
- CWF-2016-06-Bid-Set-Specifications-website-rfs.pdf
- CWF-2016-06-Bid-Set-Design-Plans-website-rfs-1.pdf
- CWF-2016-06-II-Rehab-for-Hamden-East-Haven-Plan-Pick-Up-Sheet-6.pdf
- 200819-CWF-2016-06-Pre-Bid-Meeting-Agenda-August-19-2020-with-Teams-Meeting-Link.pdf
- 200819-CWF-2016-06-August-25-2020-at-10-AM-Field-Site-Walk-Location-Town-of-Hamden-2-1.pdf
- CWF-2016-06-_-Addendum-No.-1.pdf
- CWF-2016-06_Addendum-No.-2.pdf
- CWF-2016-06-II-Rehab-for-Hamden-East-Haven-Unofficial-Bid-Results.pdf
- CWF-2016-06-_-Bid-Tabulations.pdf