Construction Projects

The Greater New Haven Water Pollution Control Authority (GNHWPCA) funds and maintains a Capital Improvement Program (CIP) to ensure that its sewer systems are reliable, safe and efficient while at the same time contributes to protect the environment. Funding for the CIP is provided through the following sources: GNHWPCA’s annual operating budget, revenue bonds, grant reimbursements and grant/loan programs provided by the Connecticut Department of Environmental Projection (DEP) along with other incidental projects required by state agencies such as the Connecticut Department of Transportation (DOT.) In this section, you will find detailed information on major construction projects currently underway in the GNHWPCA Service Area. The information will provide project purpose and description as well as GNHWPCA contacts. (project descriptions from intranet projects page “community description” )
Water Street, New Haven, CT

Improvements to Regulators 034 & 025 (Project No: CWF – 2016-05 )

Solicitation Status:
Awarded
Project Phase:
Completed
Pre Bid Meeting Date:
01/17/2018 10:00 am
Bid Date:
02/08/2018 10:00 am
Notice to Proceed:
05/01/2018
End Date:
10/28/2018
This project generally consists of the installation of a new precast concrete overflow weir structure and 24” reinforced concrete pipe at Regulator 025, and construction of a masonry wall inside Regulator 034 for permanent closure. The project requires night construction and bridging excavations to reopen the roadways to normal traffic in the daytime. Construction duration is expected to be 180 calendar days.
Budget: $0

Description


This project generally consists of the installation of a new precast concrete overflow weir structure and 24” reinforced concrete pipe at Regulator 025, and construction of a masonry wall inside Regulator 034 for permanent closure. The project requires night construction and bridging excavations to reopen the roadways to normal traffic in the daytime. Construction duration is expected to be 180 calendar days.

  • Project Group:
    Construction
  • Town Of Project:
    New Haven
  • Special Instructions:
    **PLEASE NOTE**
    All plans & specs posted in the Project Document Section are strictly for REFERENCE ONLY. All bidders are required to purchase the Plans & Specs as per the attached Bid Invitation.
  • Project Manager:
    Mario Ricozzi
  • Project Manager Address:
    GNHWPCA
    260 East Street
    New Haven, CT 06511
  • Project Manager Email:
    mricozzi@gnhwpca.com
  • Contract Duration:
    180