The Greater New Haven Water Pollution Control Authority (GNHWPCA) funds and maintains a Capital Improvement Program (CIP) to ensure that its sewer systems are reliable, safe and efficient while at the same time contributes to protect the environment. Funding for the CIP is provided through the following sources: GNHWPCA’s annual operating budget, revenue bonds, grant reimbursements and grant/loan programs provided by the Connecticut Department of Environmental Projection (DEP) along with other incidental projects required by state agencies such as the Connecticut Department of Transportation (DOT.) In this section, you will find detailed information on major construction projects currently underway in the GNHWPCA Service Area. The information will provide project purpose and description as well as GNHWPCA contacts. (project descriptions from intranet projects page “community description” )

Improving Fats, Oils, and Grease Receivings (Project No: SSF 2020-03)

Solicitation Status:
Current
Project Phase:
Bidding
Pre Bid Meeting Date:
01/04/2024 10:00 am
Bid Date:
02/15/2024 10:30 am
Notice to Proceed:
04/01/2024
End Date:
09/23/2025
Budget:

Description


The purpose of the proposal project is to demolish an existing below grade fuel storage tank, replace it with a new above ground fuel storage tank, and construct FOG Receiving Improvements. The project duration is 540 days from the notice to proceed date.

  • Project Group:
    Construction
  • Town Of Project:
    New Haven
  • Special Instructions:
    ***PLEASE NOTE*** All Plans & Specs posted in the Project Document Section are strictly for REFERENCE ONLY. All bidders are required to purchase the Plans & Specs as per the attached Bid Invitation.
  • Project Manager:
    Nick Stevens
  • Project Manager Address:
    GNHWPCA 260 East Street New Haven, CT 06511
  • Project Manager Email:
    nstevens@gnhwpca.com
  • Contract Duration:
    540 Days