Construction Projects

The Greater New Haven Water Pollution Control Authority (GNHWPCA) funds and maintains a Capital Improvement Program (CIP) to ensure that its sewer systems are reliable, safe and efficient while at the same time contributes to protect the environment. Funding for the CIP is provided through the following sources: GNHWPCA’s annual operating budget, revenue bonds, grant reimbursements and grant/loan programs provided by the Connecticut Department of Environmental Projection (DEP) along with other incidental projects required by state agencies such as the Connecticut Department of Transportation (DOT.) In this section, you will find detailed information on major construction projects currently underway in the GNHWPCA Service Area. The information will provide project purpose and description as well as GNHWPCA contacts. (project descriptions from intranet projects page “community description” )
260 East Street New Haven, CT 06511

SMALL Diameter Collection System Assessment and Rehabilitation Program (Project No: SSR 2019-02)

Solicitation Status:
Awarded
Project Phase:
Completed
Pre Bid Meeting Date:
06/12/2019 10:00 am
Bid Date:
06/27/2019 10:00 am
Notice to Proceed:
07/23/2019
End Date:
10/31/2019
Budget:

Description


The proposed project includes the cured-in-place pipe (CIPP) lining rehabilitation of approximately 9,500 feet of SMALL diameter sewer mains of various sizes from 8" to 18" sewer mains.

  • Project Group:
    Construction
  • Town Of Project:
    New Haven
  • Special Instructions:
    ***PLEASE NOTE*** All Plans & Specs posted in the Project Document Section are strictly for REFERENCE ONLY. All bidders are required to purchase the Plans & Specs as per the attached Bid Invitation.
  • Project Manager:
    Ricardo Ceballos
  • Project Manager Address:
    GNHWPCA 260 East Street New Haven, CT 06511
  • Project Manager Email:
    rceballos@gnhwpca.com
  • Contract Duration:
    90 days