South Frontage Road Sewer Rehabilitation (Project No: SSR 2021-02)
Solicitation Status:
Awarded
Awarded
Project Phase:
Completed
Completed
Pre Bid Meeting Date:
03/22/2021 2:00 pm
03/22/2021 2:00 pm
Bid Date:
03/31/2021 10:00 am
03/31/2021 10:00 am
Notice to Proceed:
04/30/2021
04/30/2021
End Date:
06/30/2021
06/30/2021
Budget:
Description
Cured-In-Place Pipe (CIPP) lining rehabilitation of approximately 2,261feet of sewer mains of various sizes including 12", 18", 20"x30" brick sewers, and 30" RCP sewer mains located in New Haven, Connecticut
- Project Group:
Construction - Town Of Project:
New Haven - Special Instructions:
*** PLEASE NOTE*** All Plans & Specs posted in the Project Document Section are strictly for REFERENCE ONLY. All bidders are required to purchase the Plans & Specs as per the attached Bid Invitation.
- Project Manager:
Ricardo Ceballos - Project Manager Address:
GNHWPCA 260 East Street New Haven, CT 06511 - Project Manager Email:
rceballos@gnhwpca.com
- Contract Duration:
60 Days