Construction Projects
43 Main Street, East Haven, CT, USA
Main Street Pump Station Cabinet Relocation & Rehabilitation (Project No: SSF – 2014-03 )
Solicitation Status:
Awarded
Awarded
Project Phase:
Completed
Completed
Pre Bid Meeting Date:
04/01/2015 10:00 am
04/01/2015 10:00 am
Bid Date:
04/16/2015 10:00 am
04/16/2015 10:00 am
Notice to Proceed:
05/22/2015
05/22/2015
End Date:
10/29/2015
10/29/2015
This Project involves relocation of the electrical panel and ancillary equipment to accommodate the DOT's improvement/realignment of the Route 1/Route 100 Intersection. The electrical panel will be relocated; the valve pit and wet well tops will be reset to the new grades. All electrical and mechanical equipment will be replaced as part of this project including new pumps. The existing wet well will stay in its current location.
Budget: $100,000
Description
This Project involves relocation of the electrical panel and ancillary equipment to accommodate the DOT's improvement/realignment of the Route 1/Route 100 Intersection. The electrical panel will be relocated; the valve pit and wet well tops will be reset to the new grades. All electrical and mechanical equipment will be replaced as part of this project including new pumps. The existing wet well will stay in its current location.
- Project Group:
Construction - Town Of Project:
East Haven - Special Instructions:
*PLEASE NOTE* All Plans & Specs posted in the Project Document Section are strictly for Reference Only. All Bidders are required to purchase these plans & specs as per the attached Bid Invitation.
The attached DOT Project Plans (Bid Separately by DOT) are for reference only.
- Project Manager:
Tom Sgroi - Project Manager Address:
260 East Street
New Haven, CT 06511 - Project Manager Email:
engineering@gnhwpca.com
- Contract Duration:
160