The Greater New Haven Water Pollution Control Authority (GNHWPCA) funds and maintains a Capital Improvement Program (CIP) to ensure that its sewer systems are reliable, safe and efficient while at the same time contributes to protect the environment. Funding for the CIP is provided through the following sources: GNHWPCA’s annual operating budget, revenue bonds, grant reimbursements and grant/loan programs provided by the Connecticut Department of Environmental Projection (DEP) along with other incidental projects required by state agencies such as the Connecticut Department of Transportation (DOT.) In this section, you will find detailed information on major construction projects currently underway in the GNHWPCA Service Area. The information will provide project purpose and description as well as GNHWPCA contacts. (project descriptions from intranet projects page “community description” )
43 Main Street, East Haven, CT, USA

Main Street Pump Station Cabinet Relocation & Rehabilitation (Project No: SSF – 2014-03 )

Solicitation Status:
Awarded
Project Phase:
Completed
Pre Bid Meeting Date:
04/01/2015 10:00 am
Bid Date:
04/16/2015 10:00 am
Notice to Proceed:
05/22/2015
End Date:
10/29/2015
This Project involves relocation of the electrical panel and ancillary equipment to accommodate the DOT's improvement/realignment of the Route 1/Route 100 Intersection. The electrical panel will be relocated; the valve pit and wet well tops will be reset to the new grades. All electrical and mechanical equipment will be replaced as part of this project including new pumps. The existing wet well will stay in its current location.
Budget: $100,000

Description


This Project involves relocation of the electrical panel and ancillary equipment to accommodate the DOT's improvement/realignment of the Route 1/Route 100 Intersection. The electrical panel will be relocated; the valve pit and wet well tops will be reset to the new grades. All electrical and mechanical equipment will be replaced as part of this project including new pumps. The existing wet well will stay in its current location.

  • Project Group:
    Construction
  • Town Of Project:
    East Haven
  • Special Instructions:
    *PLEASE NOTE* All Plans & Specs posted in the Project Document Section are strictly for Reference Only. All Bidders are required to purchase these plans & specs as per the attached Bid Invitation.
    The attached DOT Project Plans (Bid Separately by DOT) are for reference only.
  • Project Manager:
    Tom Sgroi
  • Project Manager Address:
    260 East Street
    New Haven, CT 06511
  • Project Manager Email:
    engineering@gnhwpca.com
  • Contract Duration:
    160