Construction Projects
Yale Campus/Trumbull St. Area Sewer Separation Project: Phase 2 (Project No: CWF 2012-04)
Solicitation Status:
Awarded
Awarded
Project Phase:
Construction
Construction
Pre Bid Meeting Date:
06/16/2022 11:00 am
06/16/2022 11:00 am
Bid Date:
07/12/2022 10:00 am
07/12/2022 10:00 am
Notice to Proceed:
03/01/2023
03/01/2023
End Date:
06/28/2024
06/28/2024
Budget:
Description
This project consists of the installation of approximately 6,050 linear feet of 15" to 42" RCP storm sewers, 320 linear feet of 12” PVC sanitary sewers and PVC laterals utilizing open cut excavation, storm and sanitary sewer manholes, and other appurtenances, and surface restoration. The project also includes the installation of green infrastructure components including 22 bioswales, 45 infiltrating catch basins, and 7 bump-out bioswales at various locations.
- Project Group:
Construction - Town Of Project:
New Haven - Special Instructions:
** PLEASE NOTE** All Plans & Specs posted in the Project Document Section are strictly for REFERENCE COPY ONLY. All bidders are required to purchase the Plans & Specs as per the Bid Invitation.
- Project Manager:
Mario Ricozzi - Project Manager Address:
GNHWPCA 260 East Street New Haven, CT 06511 - Project Manager Email:
mricozzi@gnhwpca.com
- Contract Duration:
485 Days
Project Documents:
- 220610_Invitation-Trumbull-St-Separation-Final.pdf
- Trumbull-Phase-2-Bid-Specs-Binder-Web-Protected.pdf
- Trumbull-Plan-Bid-Set_06-03-2022-Part-1-of-3-Web-Protected.pdf
- Trumbull-Plan-Bid-Set_06-03-2022-Part-2-of-3-Web-Protected.pdf
- Trumbull-Plan-Bid-Set_06-03-2022-Part-3-of-3-Web-Protected.pdf
- 220616-CWF-2012-04-2019-05-Pre-Bid-Meeting-Notice-1.pdf
- CWF-2012-04-Trumbull-Phase-2-Plan-Pick-Up-Sheet-8.pdf
- 220623-CWF-2012-04-Addendum-1-Yale-Campus-Trumbull-St-Area-Sewer-Separation-June-23-2022-w-enclosures-RFSz.pdf
- 220701CWF-2012-04-Addendum-2-Yale-Campus-Trumbull-St-Area-Sewer-Separation-July-01-2022.pdf
- 220715-CWF-2012-04-Addendum-3-Yale-Campus-Trumbull-St-Area-Sewer-Separation-July-15-2022-w-encl-RFSz.pdf
- CWF-2012-04-Yale-Trumbull-St-Phase-2-Unofficial-Bid-Results.pdf
- CWF-2012-04-Yale-Trumbull-St-Phase-2-Unofficial-Bid-Results-1.pdf